Jig Boring Machine in a production cell: cycle time and capacity

Jig Boring Machine is a machine built to position holes accurately, with a thermally stable structure and precision scales. It is used for hole patterns where the position between holes matters more than the hole size. This entry explains what it is, what the numbers on a data sheet mean, and what to put on a drawing.
It is written from the point of view of the buyer and the drawing office: the values that are realistic in production, the ones that cost money, and the way the result is verified. Where an industry sets the requirement, oil and gas is used as the example: materials that work harden and still have to be certified.
Cycle time
A realistic cycle for Jig Boring Machine is 1 to 4 hours for a plate. That figure includes handling and measurement, not just the cutting, because the part has to be taken out, checked and put back.
Capacity planning
Capacity is planned on available hours, not on nominal hours: setup, maintenance and measurement all take a share. Where a batch repeats, the setup is amortised and the effective capacity rises sharply.
Bottlenecks
- Pattern complexity and the number of size changes, which is the usual limit on a single machine.
- Inspection, which queues when a batch is released at the end of a shift.
- Material availability, because 6082-T6 aluminium has to be on the bar before the machine can start.
| Item | Note |
|---|---|
| Cycle | 1 to 4 hours for a plate |
| Cost driver | pattern complexity and the number of size changes |
| Tolerance | ±0.005 mm |
| Material | 6082-T6 aluminium |
| Documentation | in-house approval with dimensional reports |

Applications
Jig Boring Machine is used for hole patterns where the position between holes matters more than the hole size, and in practice it appears most often in jig plates, mould plates, indexing fixtures, instrument bodies.
How it fits into a machining route
Jig Boring Machine is one station in a route rather than the whole of it. The part arrives with the previous operation finished and leaves with the features it is responsible for completed, so the datum and the clamping method are agreed before the first part rather than discovered on it.The route is fixed before the first part is cut, and it is the route rather than the individual setting that holds the result: pattern complexity and the number of size changes. Where a drawing calls for something the route cannot hold economically, that is raised at quotation rather than after the parts are made.
Standards, documentation and what is issued
The documentation requirement is in-house approval with dimensional reports. Material is supplied against a certificate where the application calls for it, inspection results are recorded with the job, and the records are kept so that a repeat order can be compared with the first instead of being measured from scratch.
CMM for the pattern, bore gauge for the sizes is the verification step. Where a customer format or a standard report is required, it is agreed before the batch starts, because a report written after the event is a report nobody can use.
Frequently asked questions
What tolerance should be specified for Jig Boring Machine?
±0.005 mm is realistic in production. Tightening it beyond the functional requirement increases cost without improving the part.
Which material is usually used?
6082-T6 aluminium is the usual choice, supplied against in-house approval with dimensional reports.
How is the result verified?
CMM for the pattern, bore gauge for the sizes, with the results recorded so a repeat order can be compared with the first.
What is the most common mistake?
Temperature drift during a long job.
How long does it take and what does it cost?
A realistic cycle is 1 to 4 hours for a plate, and the cost driver is pattern complexity and the number of size changes.

Related capability
If you are specifying Jig Boring Machine on a drawing and want a second opinion on the route, send the model and the quantity. The first response is a manufacturability review with the likely risk points and a quotation, so the decision can be made on facts rather than on a price alone.